N84 Grid

Legacy 400kV Substation

NESO connection site, host NGET.

Contracted here1.71 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Aug 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue1,714 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Legacy Tertiary Connection31 May 202431 Aug 202457 MW
Legacy Green Energy Centre31 May 202430 Oct 2027400 MW
Plas Power Estate North Tertiary31 May 202431 May 202857 MW
Legacy Green Energy Centre31 May 202428 Oct 2037800 MW
Legacy 40031 May 202430 Oct 2037400 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2024: 57 MW2027: 457 MW2028: 514 MW2037: 1.7 GW20242026202820302032203420371.7 GW
0 MW1.0 GW2.0 GW2024: 57 MW2027: 457 MW2028: 514 MW2037: 1.7 GW20242028203220371.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202457 MW
2027457 MW
2028514 MW
20371,714 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Legacy Tertiary Connection57 MW0 MW31 Aug 2024not statedgate not printedConsents Approved
2Legacy Green Energy Centre400 MW57 MW30 Oct 20271gate 1Awaiting Consents
3Plas Power Estate North Tertiary57 MW457 MW31 May 2028not statedgate not printedScoping
4Legacy Green Energy Centre800 MW514 MW28 Oct 20371gate 1Awaiting Consents
5Legacy 400400 MW1,314 MW30 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024157 MW
20271400 MW
2028157 MW
203721,200 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Legacy Green Energy CentreBattery storage1,200 MW28 Oct 2037Awaiting Consents
Legacy 400 (ENSO GREEN HOLDINGS LIMITED)Hybrid400 MW30 Oct 2037Scoping
Legacy Tertiary ConnectionBattery storage57 MW31 Aug 2024Consents Approved
Plas Power Estate North TertiaryHybrid57 MW31 May 2028Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.