The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Legacy Tertiary Connection
31 May 2024 to 31 Aug 2024, date already passed (gate not printed) - Legacy Green Energy Centre
31 May 2024 to 30 Oct 2027 (gate 1) - Plas Power Estate North Tertiary
31 May 2024 to 31 May 2028 (gate not printed) - Legacy Green Energy Centre
31 May 2024 to 28 Oct 2037 (gate 1) - Legacy 400
31 May 2024 to 30 Oct 2037 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Legacy Tertiary Connection | 31 May 2024 | 31 Aug 2024 | 57 MW |
| Legacy Green Energy Centre | 31 May 2024 | 30 Oct 2027 | 400 MW |
| Plas Power Estate North Tertiary | 31 May 2024 | 31 May 2028 | 57 MW |
| Legacy Green Energy Centre | 31 May 2024 | 28 Oct 2037 | 800 MW |
| Legacy 400 | 31 May 2024 | 30 Oct 2037 | 400 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2024 | 57 MW |
| 2027 | 457 MW |
| 2028 | 514 MW |
| 2037 | 1,714 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Legacy Tertiary Connection | 57 MW | 0 MW | 31 Aug 2024 | not stated | gate not printed | Consents Approved |
| 2 | Legacy Green Energy Centre | 400 MW | 57 MW | 30 Oct 2027 | 1 | gate 1 | Awaiting Consents |
| 3 | Plas Power Estate North Tertiary | 57 MW | 457 MW | 31 May 2028 | not stated | gate not printed | Scoping |
| 4 | Legacy Green Energy Centre | 800 MW | 514 MW | 28 Oct 2037 | 1 | gate 1 | Awaiting Consents |
| 5 | Legacy 400 | 400 MW | 1,314 MW | 30 Oct 2037 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2024 | 1 | 57 MW |
| 2027 | 1 | 400 MW |
| 2028 | 1 | 57 MW |
| 2037 | 2 | 1,200 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Legacy Green Energy Centre | Battery storage | 1,200 MW | 28 Oct 2037 | Awaiting Consents |
| Legacy 400 (ENSO GREEN HOLDINGS LIMITED) | Hybrid | 400 MW | 30 Oct 2037 | Scoping |
| Legacy Tertiary Connection | Battery storage | 57 MW | 31 Aug 2024 | Consents Approved |
| Plas Power Estate North Tertiary | Hybrid | 57 MW | 31 May 2028 | Scoping |
Supported by National Energy SO Open Data