Ayre (ex Cluaran Ear - Thuath) Offshore Wind Farm

Developer as published, connection site, reference: AYRE OFFSHORE WIND FARM LIMITED. Banniskirk 400kV Substation (SHET). PRO-002100.

Sign in to watch this project
Capacity1,008 MWOffshore wind
Connection date31 Oct 2033Status as printed: Awaiting Consents
MW ahead in N84's order at this site2,250 MWcalculated by N84

Connection date, edition by edition

20332034File dated 2024-05-31: connection date 2033-10-31Oct 2033File dated 2026-10-20: connection date 2033-10-3131 May202420 Oct2026
20332034File dated 2024-05-31: connection date 2033-10-31Oct 2033File dated 2026-10-20: connection date 2033-10-3131 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Awaiting Consents (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Awaiting ConsentsReceipt: NESO TEC Register, file dated 20 Oct 2026, row 104Receipt: NESO TEC Register, file dated 11 Sep 2026, row 104