N84 Grid

Drum Farm Energy Storage Facility

Developer as published, connection site, reference: Field Drum Farm Ltd. Keith 2 132/33kV GSP Substation (SHET). PRO-001726.

Sign in to watch this project
Capacity49.9 MWBattery storage, Gate 2
Connection date31 Oct 2026Status as printed: Consents Approved
First date seen 31 Oct 2028, difference -731 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

2026202720282029File dated 2026-09-11: connection date 2028-10-31Oct 2028File dated 2026-10-20: connection date 2026-10-31Oct 202611 Sep202620 Oct2026
2026202720282029File dated 2026-09-11: connection date 2028-10-31Oct 2028File dated 2026-10-20: connection date 2026-10-31Oct 202611 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Consents Approved (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 634Receipt: NESO TEC Register, file dated 11 Sep 2026, row 625
  2. 20 Oct 2026. MW Effective From printed as 31 Oct 2026 (previous file: 31 Oct 2028), 731 days earlier. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. -731 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 634Receipt: NESO TEC Register, file dated 11 Sep 2026, row 625

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.