N84 Grid

Keith 2 132/33kV GSP Substation

NESO connection site, host SHET.

Contracted here0.13 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue132.1 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Drum Farm Energy Storage Facility31 May 202431 Oct 202649.9 MW
Garbet Wind Farm31 May 202431 Oct 202646.2 MW
Hill of Towie 2 Wind Farm31 May 20241 Jun 203036 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 96 MW2030: 132 MW20262027202820292030132 MW
0 MW100 MW200 MW2026: 96 MW2030: 132 MW202620282030132 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202696.1 MW
2030132.1 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Drum Farm Energy Storage Facility49.9 MW0 MW31 Oct 20262gate 2Consents Approved
2Garbet Wind Farm46.2 MW49.9 MW31 Oct 20262gate 2Consents Approved
3Hill of Towie 2 Wind Farm36 MW96.1 MW1 Jun 2030not statedgate not printedConsents Approved

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026296.1 MW
2030136 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Drum Farm Energy Storage FacilityBattery storage49.9 MW31 Oct 2026Consents Approved
Garbet Wind FarmOnshore wind46.2 MW31 Oct 2026Consents Approved
Hill of Towie 2 Wind FarmOnshore wind36 MW1 Jun 2030Consents Approved

Supported by National Energy SO Open Data