Swansea North Green Energy Centre

Developer as published, connection site, reference: SWANSEA NORTH GREEN NG LIMITED. Swansea North 400kV Substation (NGET). PRO-001794.

Sign in to watch this project
Capacity1,025 MWHybrid
Connection date31 Oct 2033Status as printed: Scoping
First date seen 30 Oct 2028, difference +1827 dayscalculated by N84
MW ahead in N84's order at this site61.9 MWcalculated by N84

Connection date, edition by edition

20332034File dated 2024-05-31: connection date 2033-10-31Oct 2033File dated 2026-04-17: connection date 2033-10-3131 May202417 Apr2026
20332034File dated 2024-05-31: connection date 2033-10-31Oct 2033File dated 2026-04-17: connection date 2033-10-3131 May202417 Apr2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 17 Apr 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data