Neilston 400kV Greener Grid Park

Developer as published, connection site, reference: Statkraft UK Ltd. Neilston 400kV Substation (SPT). PRO-001419.

Sign in to watch this project
Capacity600 MWBattery storage, Gate 2
Connection date31 Oct 2029Status as printed: Consents Approved
First date seen 17 May 2027, difference +898 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20292030File dated 2024-05-31: connection date 2029-10-31Oct 2029File dated 2026-10-20: connection date 2029-10-3131 May202420 Oct2026
20292030File dated 2024-05-31: connection date 2029-10-31Oct 2029File dated 2026-10-20: connection date 2029-10-3131 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Consents Approved (previous file: Awaiting Consents). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedAwaiting Consents → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1516Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1496

Supported by National Energy SO Open Data