Neilston 400kV Substation

NESO connection site, host SPT.

Contracted here1.00 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,000 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Neilston 400kV Greener Grid Park31 May 202431 Oct 2029600 MW
Hurlet Battery22 Jul 202531 Oct 2033400 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2029: 600 MW2033: 1.0 GW202920302031203220331.0 GW
0 MW500 MW1.0 GW2029: 600 MW2033: 1.0 GW2029203120331.0 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029600 MW
20331,000 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Neilston 400kV Greener Grid Park600 MW0 MW31 Oct 20292gate 2Consents Approved
2Hurlet Battery400 MW600 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291600 MW
20331400 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Neilston 400kV Greener Grid ParkBattery storage600 MW31 Oct 2029Consents Approved
Hurlet BatteryBattery storage400 MW31 Oct 2033Scoping
Neilston 132 (NEILSTON ENERGY LIMITED)Battery storage150 MW31 Oct 2025Built
Neilston Synchronous CompensationReactive compensation0 MW12 Jun 2025Consents Approved

Supported by National Energy SO Open Data