N84 Grid

Green Volt Offshore Windfarm

Developer as published, connection site, reference: FLOTATION ENERGY LIMITED. New Deer 400kV Substation (SHET). PRO-001469.

Sign in to watch this project
Capacity560 MWOffshore wind
Connection date31 Oct 2033Status as printed: Scoping
First date seen 31 Mar 2029, difference +1675 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20332034File dated 2024-05-31: connection date 2033-10-31Oct 2033File dated 2024-12-20: connection date 2033-10-3131 May202420 Dec2024
20332034File dated 2024-05-31: connection date 2033-10-31Oct 2033File dated 2024-12-20: connection date 2033-10-3131 May202420 Dec2024

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Dec 2024. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.