New Deer 400kV Substation

NESO connection site, host SHET.

Contracted here0.76 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Mar 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue760 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Green Volt Offshore Windfarm31 May 202431 Mar 2029300 MW
Zenobe New Deer Battery Storage31 May 202431 Oct 2029200 MW
Green Volt Offshore Windfarm31 May 202431 Oct 2033260 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2029: 500 MW2033: 760 MW20292030203120322033760 MW
0 MW400 MW800 MW2029: 500 MW2033: 760 MW202920312033760 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029500 MW
2033760 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Green Volt Offshore Windfarm300 MW0 MW31 Mar 2029not statedgate not printedScoping
2Zenobe New Deer Battery Storage200 MW300 MW31 Oct 2029not statedgate not printedScoping
3Green Volt Offshore Windfarm260 MW500 MW31 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20292500 MW
20331260 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Moray East Offshore Wind FarmOffshore wind900 MWnot statedBuilt
Green Volt Offshore WindfarmOffshore wind560 MW31 Oct 2033Scoping
Zenobe New Deer Battery StorageBattery storage200 MW31 Oct 2029Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.