N84 Grid

Thainstone Energy Park

Developer as published, connection site, reference: AGILE ENERGY RECOVERY (INVERURIE) LIMITED. Kintore GSP (SHET). PRO-001493.

Sign in to watch this project
Capacity40 MWBiomass and waste, Gate 2
Connection date31 Oct 2029Status as printed: Consents Approved
First date seen 31 Jul 2023, difference +2284 dayscalculated by N84
MW ahead in N84's order at this site49.9 MWcalculated by N84

Connection date, edition by edition

20292030File dated 2026-09-11: connection date 2029-10-30Oct 2029File dated 2026-10-20: connection date 2029-10-31Oct 202911 Sep202620 Oct2026
20292030File dated 2026-09-11: connection date 2029-10-30Oct 2029File dated 2026-10-20: connection date 2029-10-31Oct 202911 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Oct 2029 (previous file: 30 Oct 2029), 1 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +1 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 2002Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1974

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.