N84 Grid

Kintore GSP

NESO connection site, host SHET.

Contracted here2.39 GWNot yet connected, as printed
Entries in the queue12entries with a printed MW
Earliest connection date1 Jul 2022Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue153.2 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Broomhill Battery Energy Storage7 Nov 202530 Nov 202649.9 MW
Thainstone Energy Park31 May 202431 Oct 202940 MW
Fordtown Battery Storage7 Nov 20251 Jul 202249.9 MW
Kintore GSP (DNO)7 Nov 202530 Nov 20230.15 MW
Cullerlie Estate PV7 Nov 20251 May 20248.75 MW
Cairnbrogie Wind Farm7 Nov 20251 Jan 20254.5 MW
Kintore South Fordtown Energy Storage7 Nov 202531 Oct 202625 MW
Kintore South Fordtown (Leylodge)7 Nov 202531 Oct 202750 MW
Kintore South Fordtown Energy Storage7 Nov 202531 Oct 202925 MW
Alcemi Midmill BESS31 May 202431 Dec 2029300 MW
Kirkton BESS7 Nov 202531 Oct 203540 MW
North-East Offshore Hybrid Asset27 Mar 202630 Jun 20371,800 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2022: 50 MW2023: 50 MW2024: 59 MW2025: 63 MW2026: 138 MW2027: 188 MW2029: 553 MW2035: 593 MW2037: 2.4 GW202220242026202820302032203420372.4 GW
0 MW1.3 GW2.5 GW2022: 50 MW2023: 50 MW2024: 59 MW2025: 63 MW2026: 138 MW2027: 188 MW2029: 553 MW2035: 593 MW2037: 2.4 GW202220262030203420372.4 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202249.9 MW
202350.05 MW
202458.8 MW
202563.3 MW
2026138.2 MW
2027188.2 MW
2029553.2 MW
2035593.2 MW
20372,393.2 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Broomhill Battery Energy Storage49.9 MW0 MW30 Nov 20262gate 2Consents Approved
2Thainstone Energy Park40 MW49.9 MW31 Oct 20292gate 2Consents Approved
3Fordtown Battery Storage49.9 MW89.9 MW1 Jul 2022not statedgate not printedConsents Approved
4Kintore GSP (DNO)0.15 MW139.8 MW30 Nov 2023not statedgate not printedScoping
5Cullerlie Estate PV8.75 MW139.95 MW1 May 2024not statedgate not printedConsents Approved
6Cairnbrogie Wind Farm4.5 MW148.7 MW1 Jan 2025not statedgate not printedScoping
7Kintore South Fordtown Energy Storage25 MW153.2 MW31 Oct 20261gate 1Scoping
8Kintore South Fordtown (Leylodge)50 MW178.2 MW31 Oct 2027not statedgate not printedScoping
9Kintore South Fordtown Energy Storage25 MW228.2 MW31 Oct 20291gate 1Scoping
10Alcemi Midmill BESS300 MW253.2 MW31 Dec 2029not statedgate not printedScoping
11Kirkton BESS40 MW553.2 MW31 Oct 2035not statedgate not printedScoping
12North-East Offshore Hybrid Asset1,800 MW593.2 MW30 Jun 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2022149.9 MW
202310.15 MW
202418.75 MW
202514.5 MW
2026274.9 MW
2027150 MW
20293365 MW
2035140 MW
203711,800 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
North-East Offshore Hybrid AssetHybrid1,800 MW30 Jun 2037Scoping
Alcemi Midmill BESSBattery storage300 MW31 Dec 2029Scoping
Kintore South Fordtown (Leylodge)Battery storage50 MW31 Oct 2027Scoping
Kintore South Fordtown Energy StorageBattery storage50 MW31 Oct 2029Scoping
Fordtown Battery StorageBattery storage49.9 MW1 Jul 2022Consents Approved
Broomhill Battery Energy StorageBattery storage49.9 MW30 Nov 2026Consents Approved
Kirkton BESSHybrid40 MW31 Oct 2035Scoping
Thainstone Energy ParkBiomass and waste40 MW31 Oct 2029Consents Approved
Cullerlie Estate PVSolar8.75 MW1 May 2024Consents Approved
Inverurie Paper MillsThermal7.5 MWnot statedBuilt
Kirkton Wind FarmOnshore wind6.9 MWnot statedBuilt
Cairnbrogie Wind FarmOnshore wind4.5 MW1 Jan 2025Scoping
Easter TolmaudsOnshore wind2.4 MWnot statedBuilt
Hill of EastertonOnshore wind2.3 MWnot statedBuilt
Kintore GSP (DNO)Hybrid0.15 MW30 Nov 2023Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.