Strathrory Wind Farm

Developer as published, connection site, reference: STRATHRORY WIND FARM LLP. Alness GSP (SHET). PRO-001812.

Sign in to watch this project
Capacity36 MWOnshore wind
Connection date31 Mar 2024Status as printed: Consents Approved
MW ahead in N84's order at this site49.9 MWcalculated by N84

Connection date, edition by edition

20242025File dated 2024-05-31: connection date 2024-03-31Mar 2024File dated 2026-10-20: connection date 2024-03-3131 May202420 Oct2026
20242025File dated 2024-05-31: connection date 2024-03-31Mar 2024File dated 2026-10-20: connection date 2024-03-3131 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.