N84 Grid

Alness GSP

NESO connection site, host SHET.

Contracted here0.13 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Mar 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue129.1 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Balnacraig Battery Storage7 Nov 202531 Aug 202649.9 MW
Strathrory Wind Farm31 May 202431 Mar 202436 MW
Novar 2 Wind Farm21 Mar 202531 Oct 203243.2 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2024: 36 MW2026: 86 MW2032: 129 MW20242026202820302032129 MW
0 MW100 MW200 MW2024: 36 MW2026: 86 MW2032: 129 MW2024202720302032129 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202436 MW
202685.9 MW
2032129.1 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Balnacraig Battery Storage49.9 MW0 MW31 Aug 20262gate 2Consents Approved
2Strathrory Wind Farm36 MW49.9 MW31 Mar 2024not statedgate not printedConsents Approved
3Novar 2 Wind Farm43.2 MW85.9 MW31 Oct 20321gate 1Scoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024136 MW
2026149.9 MW
2032143.2 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Balnacraig Battery StorageBattery storage49.9 MW31 Aug 2026Consents Approved
Novar 2 Wind FarmOnshore wind43.2 MW31 Oct 2032Scoping
Novar 2 Wind FarmOnshore wind36.8 MWnot statedBuilt
Strathrory Wind FarmOnshore wind36 MW31 Mar 2024Consents Approved
Coire Na CloicheOnshore wind30 MWnot statedBuilt
Beinn TharsuinnOnshore wind29 MWnot statedBuilt
NovarOnshore wind18.5 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.