Capacity60 MWOnshore wind, Gate 1
Connection date29 Oct 2029Status as printed: Awaiting Consents
First date seen 31 Oct 2027, difference +729 dayscalculated by N84
First date seen 31 Oct 2027, difference +729 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84
Connection date, edition by edition
Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.
Observed changes
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. Project Status printed as Awaiting Consents (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Awaiting ConsentsReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1183Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1163
- 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1183Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1163
- 20 Oct 2026. MW Effective From printed as 29 Oct 2029 (previous file: 31 Oct 2028), 363 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +363 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1183Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1163
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.