N84 Grid

Connagill 275kV Substation

NESO connection site, host SHET.

Contracted here0.29 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date29 Oct 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue289 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Kirkton Wind Farm31 May 202429 Oct 202960 MW
Altnabreac Windfarm22 Jul 202531 Oct 2032130 MW
Forsinain Wind Farm22 Jul 202531 Oct 203799 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2029: 60 MW2032: 190 MW2037: 289 MW20292031203320352037289 MW
0 MW200 MW400 MW2029: 60 MW2032: 190 MW2037: 289 MW2029203220352037289 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202960 MW
2032190 MW
2037289 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Kirkton Wind Farm60 MW0 MW29 Oct 20291gate 1Awaiting Consents
2Altnabreac Windfarm130 MW60 MW31 Oct 2032not statedgate not printedScoping
3Forsinain Wind Farm99 MW190 MW31 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2029160 MW
20321130 MW
2037199 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Altnabreac WindfarmHybrid130 MW31 Oct 2032Scoping
Forsinain Wind FarmOnshore wind99 MW31 Oct 2037Scoping
Kirkton Wind FarmOnshore wind60 MW29 Oct 2029Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.