N84 Grid

GRUDIE BRIDGE (battery, 49.4 MW)

Developer as published, connection site, reference: GRUDIE BRIDGE. SSEN-1MW-04ee0490bc00.

Sign in to watch this project
Capacity49.4 MWBattery storage
Connection date28 Feb 2029Status as printed: Accepted to Connect
MW ahead in N84's order at this site105.9 MWcalculated by N84

Connection date, edition by edition

20292030File dated 2023-09-01: connection date 2029-02-28Feb 2029File dated 2026-10-01: connection date 2029-02-281 Sep20231 Oct2026
20292030File dated 2023-09-01: connection date 2029-02-28Feb 2029File dated 2026-10-01: connection date 2029-02-281 Sep20231 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 1 Sep 2023 to 1 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.