N84 Grid

Lightsource Ferryside PV

Developer as published, connection site, reference: Lightsource Renewable UK Development Limited. South Wales West Connection Node C 400kV (NGET). PRO-003761.

Sign in to watch this project
Capacity240 MWHybrid, Gate 1
Connection date31 Oct 2038Status as printed: Scoping
First date seen 30 Oct 2037, difference +366 dayscalculated by N84
MW ahead in N84's order at this site1,447.5 MWcalculated by N84

Connection date, edition by edition

203720382039File dated 2026-09-11: connection date 2037-10-30Oct 2037File dated 2026-10-20: connection date 2038-10-31Oct 203811 Sep202620 Oct2026
203720382039File dated 2026-09-11: connection date 2037-10-30Oct 2037File dated 2026-10-20: connection date 2038-10-31Oct 203811 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Oct 2038 (previous file: 30 Oct 2037), 366 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +366 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1263Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1243

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.