Capacity850 MWHybrid, Gate 1
Connection date31 Oct 2034Status as printed: Scoping
MW ahead in N84's order at this site3,000 MWcalculated by N84
Connection date, edition by edition
The connection date is printed the same in every file N84 holds for this project, from 22 Jul 2025 to 20 Oct 2026. Year marks on the side are 1 January.
Observed changes
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO TEC Register, file dated 20 Oct 2026, row 712Receipt: NESO TEC Register, file dated 17 Apr 2026, row 708
- 20 Oct 2026. Printed again after being absent from the previous file. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedleft_register → presentReceipt: NESO TEC Register, file dated 20 Oct 2026, row 712Receipt: NESO TEC Register, file dated 17 Apr 2026, row 708
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.