North Anglia Connection Node B 400kV Substation

NESO connection site, host NGET.

Contracted here3.85 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date31 Oct 2034Date printed in the register

The queue, in order

Order calculated by N84
First in queue3,850 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Project Number 431 May 202431 Oct 2034500 MW
Greta IV (b)20 Dec 202431 Oct 2034500 MW
Greta IV (c)20 Dec 202431 Oct 2034500 MW
Greta IV (d)20 Dec 202431 Oct 2034500 MW
Necton High Impact Energy Hub22 Jul 202531 Oct 20341,000 MW
Elmya Ryston BESS & PV22 Jul 202531 Oct 2034850 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2034: 3.9 GW20343.9 GW
0 MW2.0 GW4.0 GW2034: 3.9 GW20343.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20343,850 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Project Number 4500 MW0 MW31 Oct 20341gate 1Scoping
2Greta IV (b)500 MW500 MW31 Oct 20341gate 1Scoping
3Greta IV (c)500 MW1,000 MW31 Oct 20341gate 1Scoping
4Greta IV (d)500 MW1,500 MW31 Oct 20341gate 1Scoping
5Necton High Impact Energy Hub1,000 MW2,000 MW31 Oct 20341gate 1Scoping
6Elmya Ryston BESS & PV850 MW3,000 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203463,850 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Necton High Impact Energy HubHybrid1,000 MW31 Oct 2034Scoping
Elmya Ryston BESS & PVHybrid850 MW31 Oct 2034Scoping
Greta IV (d)Battery storage500 MW31 Oct 2034Scoping
Greta IV (c)Battery storage500 MW31 Oct 2034Scoping
Project Number 4Hybrid500 MW31 Oct 2034Scoping
Greta IV (b)Hybrid500 MW31 Oct 2034Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.