N84 Grid

Bramford Tertiary

Developer as published, connection site, reference: BRAMFORD GREEN LIMITED. Bramford 400kV Substation (NGET). PRO-000397.

Sign in to watch this project
Capacity57 MWHybrid
Connection date1 Oct 2029Status as printed: Consents Approved
First date seen 31 Oct 2023, difference +2162 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20292030File dated 2024-05-31: connection date 2029-10-01Oct 2029File dated 2025-03-21: connection date 2029-10-0131 May202421 Mar2025
20292030File dated 2024-05-31: connection date 2029-10-01Oct 2029File dated 2025-03-21: connection date 2029-10-0131 May202421 Mar2025

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 21 Mar 2025. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data