N84 Grid

Bramford 400kV Substation

NESO connection site, host NGET.

Contracted here1.16 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date16 Jul 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue1,163 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Bramford Tertiary31 May 202416 Jul 202649.9 MW
Bramford Tertiary31 May 20241 Oct 20297.1 MW
Bramford BESS31 May 202430 Nov 2029300 MW
Alcemi Bramford Battery Energy Storage Facility31 May 202430 Oct 2030500 MW
Bramford 2 GEC (Ethos Green)31 May 20241 Jul 203257 MW
ER BRF 2 Energy31 May 202430 Jul 2033249 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2026: 50 MW2029: 357 MW2030: 857 MW2032: 914 MW2033: 1.2 GW202620272028202920302031203220331.2 GW
0 MW1.0 GW2.0 GW2026: 50 MW2029: 357 MW2030: 857 MW2032: 914 MW2033: 1.2 GW20262028203020331.2 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202649.9 MW
2029357 MW
2030857 MW
2032914 MW
20331,163 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Bramford Tertiary49.9 MW0 MW16 Jul 2026not statedgate not printedConsents Approved
2Bramford Tertiary7.1 MW49.9 MW1 Oct 2029not statedgate not printedConsents Approved
3Bramford BESS300 MW57 MW30 Nov 2029not statedgate not printedConsents Approved
4Alcemi Bramford Battery Energy Storage Facility500 MW357 MW30 Oct 20301gate 1Scoping
5Bramford 2 GEC (Ethos Green)57 MW857 MW1 Jul 2032not statedgate not printedAwaiting Consents
6ER BRF 2 Energy249 MW914 MW30 Jul 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026149.9 MW
20292307.1 MW
20301500 MW
2032157 MW
20331249 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Alcemi Bramford Battery Energy Storage FacilityBattery storage500 MW30 Oct 2030Scoping
Bramford BESSBattery storage300 MW30 Nov 2029Consents Approved
ER BRF 2 EnergyHybrid249 MW30 Jul 2033Scoping
Bramford (Tertiary)Hybrid57 MWnot statedBuilt
Bramford 2 GEC (Ethos Green)Hybrid57 MW1 Jul 2032Awaiting Consents
Bramford TertiaryHybrid57 MW1 Oct 2029Consents Approved
Brook Farm BESSBattery storage49.9 MWnot statedBuilt
ThetfordBiomass and waste41 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.