NatPower Llanteg Green Energy Park

Developer as published, connection site, reference: NP SPV 30 LIMITED. South Wales West Connection Node C 400kV (NGET). PRO-004806.

Sign in to watch this project
Capacity47.5 MWBattery storage, Gate 1
Connection date31 Dec 2037Status as printed: Scoping
First date seen 31 Oct 2028, difference +3348 dayscalculated by N84
MW ahead in N84's order at this site1,400 MWcalculated by N84

Connection date, edition by edition

2028203120342037File dated 2026-09-11: connection date 2028-10-31Oct 2028File dated 2026-10-20: connection date 2037-12-31Dec 203711 Sep202620 Oct2026
2028203120342037File dated 2026-09-11: connection date 2028-10-31Oct 2028File dated 2026-10-20: connection date 2037-12-31Dec 203711 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Dec 2037 (previous file: 31 Oct 2028), 3,348 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +3348 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1497Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1477

Supported by National Energy SO Open Data