N84 Grid

Aitkenhead Farm BESS

Developer as published, connection site, reference: Aitkenhead Storage Facility Limited. Clydesmill 275/33kV (SPT). PRO-002585.

Sign in to watch this project
Capacity300 MWBattery storage, Gate 1
Connection date30 Apr 2033Status as printed: Scoping
First date seen 31 Oct 2028, difference +1642 dayscalculated by N84
MW ahead in N84's order at this site103 MWcalculated by N84

Connection date, edition by edition

2028203020322034File dated 2026-09-11: connection date 2028-10-31Oct 2028File dated 2026-10-20: connection date 2033-04-30Apr 203311 Sep202620 Oct2026
2028203020322034File dated 2026-09-11: connection date 2028-10-31Oct 2028File dated 2026-10-20: connection date 2033-04-30Apr 203311 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 30 Apr 2033 (previous file: 31 Oct 2028), 1,642 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +1642 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 40Receipt: NESO TEC Register, file dated 11 Sep 2026, row 40

Supported by National Energy SO Open Data