Capacity300 MWBattery storage, Gate 1
Connection date30 Apr 2033Status as printed: Scoping
First date seen 31 Oct 2028, difference +1642 dayscalculated by N84
First date seen 31 Oct 2028, difference +1642 dayscalculated by N84
MW ahead in N84's order at this site103 MWcalculated by N84
Connection date, edition by edition
Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.
Observed changes
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. MW Effective From printed as 30 Apr 2033 (previous file: 31 Oct 2028), 1,642 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +1642 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 40Receipt: NESO TEC Register, file dated 11 Sep 2026, row 40
Supported by National Energy SO Open Data