Drumfad Battery Storage System

Developer as published, connection site, reference: EKU ENERGY FAUNE PROJECTS (UK) LIMITED. Helensburgh 132/33kV (SPT). PRO-002419.

Sign in to watch this project
Capacity39.9 MWBattery storage, Gate 2
Connection date29 Oct 2027Status as printed: Consents Approved
First date seen 31 Oct 2027, difference -2 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20272028File dated 2024-05-31: connection date 2027-10-29Oct 2027File dated 2026-10-20: connection date 2027-10-2931 May202420 Oct2026
20272028File dated 2024-05-31: connection date 2027-10-29Oct 2027File dated 2026-10-20: connection date 2027-10-2931 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Consents Approved (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 636Receipt: NESO TEC Register, file dated 11 Sep 2026, row 627

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.