N84 Grid

EKU ENERGY FAUNE PROJECTS (UK) LIMITED

Grouped by published name, unverified. Printed as: EKU ENERGY FAUNE PROJECTS (UK) LIMITED.

Sign in to watch this developer
2Projects in the shown registers
89.8 MWTotal MW as printed
0 / 1Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Queued: 0.1 GW (100%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.0
Queued0.1
MW by technology
TechnologyProjectsMW
Battery storage289.8 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
STOR Field 9 BESSBattery storage49.9 MW30 Jul 2029ScopingInverkeithing 132/33kV
Drumfad Battery Storage SystemBattery storage39.9 MW29 Oct 2027Consents ApprovedHelensburgh 132/33kV

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.