Capacity49.4 MWBattery storage
Connection datenot statedStatus as printed: Connected
MW ahead in N84's order at this siteNot calculatedN84 orders only projects at a NESO connection site with a printed date.
Connection date, edition by edition
Only one edition so far
N84 holds one edition of this register for the project, so there is no earlier date to compare. The chart appears when a later edition is collected.
Observed changes
N84 holds 39 editions of the SSEN Embedded Capacity Register back to 1 Aug 2023. No change for this record is older than 30 days.
Showing changes in files dated from 23 Sep 2026.
- 1 Oct 2026. Printed in this file and not in the previous one. Between the files dated 1 Sep 2026 and 1 Oct 2026. Correction after an older file was importedblank → SSEN-1MW-ccd94c61d408Receipt: SSEN Embedded Capacity Register, file dated 1 Oct 2026, row 2194
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.