The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- BURGHMUIR (hybrid)
5 Jan 2023 to 30 Nov 2025, date already passed (gate not printed) - BURGHMUIR GRID (other)
21 Aug 2023 to 30 Jun 2027 (gate not printed) - BURGHMUIR GRID (solar)
28 Sep 2022 to 30 May 2029 (gate not printed) - BURGHMUIR (solar)
13 May 2024 to 31 Oct 2033 (gate not printed) - BURGHMUIR GRID (hybrid)
10 Jan 2025 to 31 Oct 2035 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| BURGHMUIR (hybrid) | 5 Jan 2023 | 30 Nov 2025 | 0.15 MW |
| BURGHMUIR GRID (other) | 21 Aug 2023 | 30 Jun 2027 | 8 MW |
| BURGHMUIR GRID (solar) | 28 Sep 2022 | 30 May 2029 | 56.93 MW |
| BURGHMUIR (solar) | 13 May 2024 | 31 Oct 2033 | 99.8 MW |
| BURGHMUIR GRID (hybrid) | 10 Jan 2025 | 31 Oct 2035 | 75 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2025 | 0.15 MW |
| 2027 | 8.15 MW |
| 2029 | 65.08 MW |
| 2033 | 164.88 MW |
| 2035 | 239.88 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | BURGHMUIR (hybrid) | 0.15 MW | 0 MW | 30 Nov 2025 | not stated | gate not printed | Accepted to Connect |
| 2 | BURGHMUIR GRID (other) | 8 MW | 0.15 MW | 30 Jun 2027 | not stated | gate not printed | Accepted to Connect |
| 3 | BURGHMUIR GRID (solar) | 56.93 MW | 8.15 MW | 30 May 2029 | not stated | gate not printed | Accepted to Connect |
| 4 | BURGHMUIR (solar) | 99.8 MW | 65.08 MW | 31 Oct 2033 | not stated | gate not printed | Accepted to Connect |
| 5 | BURGHMUIR GRID (hybrid) | 75 MW | 164.88 MW | 31 Oct 2035 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2025 | 1 | 0.15 MW |
| 2027 | 1 | 8 MW |
| 2029 | 1 | 56.93 MW |
| 2033 | 1 | 99.8 MW |
| 2035 | 1 | 75 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| BURGHMUIR GRID (hybrid, 75 MW) | Hybrid | 75 MW | 31 Oct 2035 | Accepted to Connect |
| BURGHMUIR GRID (solar, 99.8 MW) | Solar | 49.9 MW | 31 Oct 2033 | Accepted to Connect |
| BURGHMUIR GRID (solar, 56.92 MW) | Solar | 49.5 MW | 30 May 2029 | Accepted to Connect |
| BURGHMUIR GRID (battery, 49.4 MW) | Battery storage | 49.4 MW | not stated | Connected |
| BURGHMUIR GRID (battery, 1.39 MW) | Battery storage | 1.39 MW | not stated | Connected |
| BURGHMUIR GRID (hybrid, 0.15 MW) | Hybrid | 0.15 MW | 30 Nov 2025 | Accepted to Connect |
| BURGHMUIR GRID (onshore wind, 1 MW) | Onshore wind | 0 MW | not stated | Accepted to Connect |
| BURGHMUIR GRID (battery, 49.4 MW) | Battery storage | 0 MW | 23 May 2025 | Accepted to Connect |
| BURGHMUIR GRID (solar, 2.9 MW) | Solar | 0 MW | not stated | Connected |
| BURGHMUIR GRID (other, 49.9 MW) | Other | 0 MW | 31 Oct 2028 | Accepted to Connect |
| BURGHMUIR GRID (solar, 1.24 MW) | Solar | 0 MW | 30 Dec 2027 | Accepted to Connect |
| BURGHMUIR GRID (other, 48.12 MW) | Other | 0 MW | not stated | Accepted to Connect |
| BURGHMUIR GRID (solar, 31.61 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| BURGHMUIR GRID (solar, 1.24 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| BURGHMUIR GRID (battery, 49.9 MW) | Battery storage | 0 MW | 30 Nov 2026 | Accepted to Connect |
| BURGHMUIR GRID (battery, 51.75 MW) | Battery storage | 0 MW | 31 Oct 2033 | Accepted to Connect |
| BURGHMUIR GRID (battery, 49.4 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| BURGHMUIR GRID (battery, 51.75 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| BURGHMUIR GRID (other, 8 MW) | Other | 0 MW | 30 Jun 2027 | Accepted to Connect |
| BURGHMUIR GRID (battery, 61.46 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| BURGHMUIR GRID (solar, 56.92 MW) | Solar | 0 MW | not stated | Accepted to Connect |
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.