N84 Grid

BURGHMUIR GRID

DNO substation.

Contracted here0.24 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date30 Nov 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue239.88 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
BURGHMUIR (hybrid)5 Jan 202330 Nov 20250.15 MW
BURGHMUIR GRID (other)21 Aug 202330 Jun 20278 MW
BURGHMUIR GRID (solar)28 Sep 202230 May 202956.93 MW
BURGHMUIR (solar)13 May 202431 Oct 203399.8 MW
BURGHMUIR GRID (hybrid)10 Jan 202531 Oct 203575 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2025: 0 MW2027: 8 MW2029: 65 MW2033: 165 MW2035: 240 MW202520272029203120332035240 MW
0 MW125 MW250 MW2025: 0 MW2027: 8 MW2029: 65 MW2033: 165 MW2035: 240 MW2025202820312035240 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20250.15 MW
20278.15 MW
202965.08 MW
2033164.88 MW
2035239.88 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1BURGHMUIR (hybrid)0.15 MW0 MW30 Nov 2025not statedgate not printedAccepted to Connect
2BURGHMUIR GRID (other)8 MW0.15 MW30 Jun 2027not statedgate not printedAccepted to Connect
3BURGHMUIR GRID (solar)56.93 MW8.15 MW30 May 2029not statedgate not printedAccepted to Connect
4BURGHMUIR (solar)99.8 MW65.08 MW31 Oct 2033not statedgate not printedAccepted to Connect
5BURGHMUIR GRID (hybrid)75 MW164.88 MW31 Oct 2035not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202510.15 MW
202718 MW
2029156.93 MW
2033199.8 MW
2035175 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
BURGHMUIR GRID (hybrid, 75 MW)Hybrid75 MW31 Oct 2035Accepted to Connect
BURGHMUIR GRID (solar, 99.8 MW)Solar49.9 MW31 Oct 2033Accepted to Connect
BURGHMUIR GRID (solar, 56.92 MW)Solar49.5 MW30 May 2029Accepted to Connect
BURGHMUIR GRID (battery, 49.4 MW)Battery storage49.4 MWnot statedConnected
BURGHMUIR GRID (battery, 1.39 MW)Battery storage1.39 MWnot statedConnected
BURGHMUIR GRID (hybrid, 0.15 MW)Hybrid0.15 MW30 Nov 2025Accepted to Connect
BURGHMUIR GRID (onshore wind, 1 MW)Onshore wind0 MWnot statedAccepted to Connect
BURGHMUIR GRID (battery, 49.4 MW)Battery storage0 MW23 May 2025Accepted to Connect
BURGHMUIR GRID (solar, 2.9 MW)Solar0 MWnot statedConnected
BURGHMUIR GRID (other, 49.9 MW)Other0 MW31 Oct 2028Accepted to Connect
BURGHMUIR GRID (solar, 1.24 MW)Solar0 MW30 Dec 2027Accepted to Connect
BURGHMUIR GRID (other, 48.12 MW)Other0 MWnot statedAccepted to Connect
BURGHMUIR GRID (solar, 31.61 MW)Solar0 MWnot statedAccepted to Connect
BURGHMUIR GRID (solar, 1.24 MW)Solar0 MWnot statedAccepted to Connect
BURGHMUIR GRID (battery, 49.9 MW)Battery storage0 MW30 Nov 2026Accepted to Connect
BURGHMUIR GRID (battery, 51.75 MW)Battery storage0 MW31 Oct 2033Accepted to Connect
BURGHMUIR GRID (battery, 49.4 MW)Battery storage0 MWnot statedAccepted to Connect
BURGHMUIR GRID (battery, 51.75 MW)Battery storage0 MWnot statedAccepted to Connect
BURGHMUIR GRID (other, 8 MW)Other0 MW30 Jun 2027Accepted to Connect
BURGHMUIR GRID (battery, 61.46 MW)Battery storage0 MWnot statedAccepted to Connect
BURGHMUIR GRID (solar, 56.92 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.