Elmya Melbourne BESS

Developer as published, connection site, reference: ELMYA RPC UK MELBOURNE LIMITED. Thornton 400kV Substation (NGET). PRO-002424.

Sign in to watch this project
Capacity300 MWBattery storage, Gate 1
Connection date28 Oct 2039Status as printed: Scoping
First date seen 28 Oct 2033, difference +2191 dayscalculated by N84
MW ahead in N84's order at this site1,490.01 MWcalculated by N84

Connection date, edition by edition

20392040File dated 2024-05-31: connection date 2039-10-28Oct 2039File dated 2025-07-22: connection date 2039-10-2831 May202422 Jul2025
20392040File dated 2024-05-31: connection date 2039-10-28Oct 2039File dated 2025-07-22: connection date 2039-10-2831 May202422 Jul2025

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 22 Jul 2025. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO TEC Register, file dated 20 Oct 2026, row 709Receipt: NESO TEC Register, file dated 11 Sep 2026, row 693
  2. 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO TEC Register, file dated 20 Oct 2026, row 708Receipt: NESO TEC Register, file dated 11 Sep 2026, row 692

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.