The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Thornton Facility
31 May 2024 to 29 Oct 2027 (gate not printed) - Thornton Facility
31 May 2024 to 30 Nov 2028 (gate not printed) - Thornton
31 May 2024 to 31 Oct 2031 (gate not printed) - Derwent Solar PV Array
31 May 2024 to 31 May 2032 (gate not printed) - Thornton Facility
31 May 2024 to 29 Oct 2032 (gate not printed) - Elmya Melbourne BESS
31 May 2024 to 28 Oct 2033 (gate 1) - Elmya Melbourne BESS
31 May 2024 to 28 Oct 2039 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Thornton Facility | 31 May 2024 | 29 Oct 2027 | 99.98 MW |
| Thornton Facility | 31 May 2024 | 30 Nov 2028 | 200 MW |
| Thornton | 31 May 2024 | 31 Oct 2031 | 500 MW |
| Derwent Solar PV Array | 31 May 2024 | 31 May 2032 | 160 MW |
| Thornton Facility | 31 May 2024 | 29 Oct 2032 | 530.03 MW |
| Elmya Melbourne BESS | 31 May 2024 | 28 Oct 2033 | 252 MW |
| Elmya Melbourne BESS | 31 May 2024 | 28 Oct 2039 | 48 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 99.98 MW |
| 2028 | 299.98 MW |
| 2031 | 799.98 MW |
| 2032 | 1,490.01 MW |
| 2033 | 1,742.01 MW |
| 2039 | 1,790.01 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Thornton Facility | 99.98 MW | 0 MW | 29 Oct 2027 | not stated | gate not printed | Consents Approved |
| 2 | Thornton Facility | 200 MW | 99.98 MW | 30 Nov 2028 | not stated | gate not printed | Consents Approved |
| 3 | Thornton | 500 MW | 299.98 MW | 31 Oct 2031 | not stated | gate not printed | Scoping |
| 4 | Derwent Solar PV Array | 160 MW | 799.98 MW | 31 May 2032 | not stated | gate not printed | Scoping |
| 5 | Thornton Facility | 530.03 MW | 959.98 MW | 29 Oct 2032 | not stated | gate not printed | Consents Approved |
| 6 | Elmya Melbourne BESS | 252 MW | 1,490.01 MW | 28 Oct 2033 | 1 | gate 1 | Awaiting Consents |
| 7 | Elmya Melbourne BESS | 48 MW | 1,742.01 MW | 28 Oct 2039 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 99.98 MW |
| 2028 | 1 | 200 MW |
| 2031 | 1 | 500 MW |
| 2032 | 2 | 690.03 MW |
| 2033 | 1 | 252 MW |
| 2039 | 1 | 48 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Thornton Facility | Hybrid | 929.99 MW | 29 Oct 2032 | Consents Approved |
| Thornton (IGP SOLAR 19 LIMITED) | Hybrid | 500 MW | 31 Oct 2031 | Scoping |
| Elmya Melbourne BESS | Battery storage | 300 MW | 28 Oct 2039 | Scoping |
| Derwent Solar PV Array | Solar | 160 MW | 31 May 2032 | Scoping |
| Zenobe Thornton BESS | Battery storage | 0 MW | 30 Oct 2035 | Scoping |