Thornton 400kV Substation

NESO connection site, host NGET.

Contracted here1.79 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date29 Oct 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,742.01 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Thornton Facility31 May 202429 Oct 202799.98 MW
Thornton Facility31 May 202430 Nov 2028200 MW
Thornton31 May 202431 Oct 2031500 MW
Derwent Solar PV Array31 May 202431 May 2032160 MW
Thornton Facility31 May 202429 Oct 2032530.03 MW
Elmya Melbourne BESS31 May 202428 Oct 2033252 MW
Elmya Melbourne BESS31 May 202428 Oct 203948 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2027: 100 MW2028: 300 MW2031: 800 MW2032: 1.5 GW2033: 1.7 GW2039: 1.8 GW20272029203120332035203720391.8 GW
0 MW1.0 GW2.0 GW2027: 100 MW2028: 300 MW2031: 800 MW2032: 1.5 GW2033: 1.7 GW2039: 1.8 GW20272031203520391.8 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202799.98 MW
2028299.98 MW
2031799.98 MW
20321,490.01 MW
20331,742.01 MW
20391,790.01 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Thornton Facility99.98 MW0 MW29 Oct 2027not statedgate not printedConsents Approved
2Thornton Facility200 MW99.98 MW30 Nov 2028not statedgate not printedConsents Approved
3Thornton500 MW299.98 MW31 Oct 2031not statedgate not printedScoping
4Derwent Solar PV Array160 MW799.98 MW31 May 2032not statedgate not printedScoping
5Thornton Facility530.03 MW959.98 MW29 Oct 2032not statedgate not printedConsents Approved
6Elmya Melbourne BESS252 MW1,490.01 MW28 Oct 20331gate 1Awaiting Consents
7Elmya Melbourne BESS48 MW1,742.01 MW28 Oct 20391gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027199.98 MW
20281200 MW
20311500 MW
20322690.03 MW
20331252 MW
2039148 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Thornton FacilityHybrid929.99 MW29 Oct 2032Consents Approved
Thornton (IGP SOLAR 19 LIMITED)Hybrid500 MW31 Oct 2031Scoping
Elmya Melbourne BESSBattery storage300 MW28 Oct 2039Scoping
Derwent Solar PV ArraySolar160 MW31 May 2032Scoping
Zenobe Thornton BESSBattery storage0 MW30 Oct 2035Scoping

Supported by National Energy SO Open Data