N84 Grid

Ninfield

Developer as published, connection site, reference: Ninfield 10 Renewables Limited. Sussex and Romney Connection Node A 400kV Substation (NGET). PRO-003408.

Sign in to watch this project
Capacity1,000 MWHybrid, Gate 1
Connection date31 Oct 2037Status as printed: Scoping
First date seen 31 Oct 2030, difference +2557 dayscalculated by N84
MW ahead in N84's order at this site57 MWcalculated by N84

Connection date, edition by edition

20302032203420362038File dated 2026-09-11: connection date 2030-10-31Oct 2030File dated 2026-10-20: connection date 2037-10-31Oct 203711 Sep202620 Oct2026
20302032203420362038File dated 2026-09-11: connection date 2030-10-31Oct 2030File dated 2026-10-20: connection date 2037-10-31Oct 203711 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Oct 2037 (previous file: 31 Oct 2030), 2,557 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +2557 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1546Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1526

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.