Hawthorn BESS

Developer as published, connection site, reference: REWE 8 LIMITED. Wearside Connection Node B 400kV Substation (NGET). PRO-003492.

Sign in to watch this project
Capacity200 MWBattery storage, Gate 1
Connection date30 Oct 2035Status as printed: Awaiting Consents
First date seen 31 Oct 2033, difference +729 dayscalculated by N84
MW ahead in N84's order at this site1,800 MWcalculated by N84

Connection date, edition by edition

2033203420352036File dated 2026-09-11: connection date 2033-10-31Oct 2033File dated 2026-10-20: connection date 2035-10-30Oct 203511 Sep202620 Oct2026
2033203420352036File dated 2026-09-11: connection date 2033-10-31Oct 2033File dated 2026-10-20: connection date 2035-10-30Oct 203511 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 30 Oct 2035 (previous file: 31 Oct 2033), 729 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +729 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 999Receipt: NESO TEC Register, file dated 11 Sep 2026, row 979

Supported by National Energy SO Open Data