Gresham House Cockenzie BESS

Developer as published, connection site, reference: COCKENZIE STORAGE LIMITED. Meadowmill 400/132kV Substation (SPT). PRO-002209.

Sign in to watch this project
Capacity240 MWBattery storage, Gate 2
Connection date31 Jul 2027Status as printed: Under Construction/Commissioning
First date seen 31 Jul 2026, difference +365 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20272028File dated 2024-05-31: connection date 2027-07-31Jul 2027File dated 2026-10-20: connection date 2027-07-3131 May202420 Oct2026
20272028File dated 2024-05-31: connection date 2027-07-31Jul 2027File dated 2026-10-20: connection date 2027-07-3131 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Under Construction/Commissioning (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Under Construction/CommissioningReceipt: NESO TEC Register, file dated 20 Oct 2026, row 942Receipt: NESO TEC Register, file dated 11 Sep 2026, row 921

Supported by National Energy SO Open Data