The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Gresham House Cockenzie BESS
31 May 2024 to 31 Jul 2027 (gate 2) - Cockenzie BESS
31 May 2024 to 31 Jul 2027 (gate 2)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Gresham House Cockenzie BESS | 31 May 2024 | 31 Jul 2027 | 240 MW |
| Cockenzie BESS | 31 May 2024 | 31 Jul 2027 | 102 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 342 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Gresham House Cockenzie BESS | 240 MW | 0 MW | 31 Jul 2027 | 2 | gate 2 | Under Construction/Commissioning |
| 2 | Cockenzie BESS | 102 MW | 240 MW | 31 Jul 2027 | 2 | gate 2 | Under Construction/Commissioning |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 2 | 342 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Gresham House Cockenzie BESS | Battery storage | 240 MW | 31 Jul 2027 | Under Construction/Commissioning |
| Cockenzie BESS | Battery storage | 102 MW | 31 Jul 2027 | Under Construction/Commissioning |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.