Meadowmill 400/132kV Substation

NESO connection site, host SPT.

Contracted here0.34 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Jul 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue342 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Gresham House Cockenzie BESS31 May 202431 Jul 2027240 MW
Cockenzie BESS31 May 202431 Jul 2027102 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2027: 342 MW2027342 MW
0 MW200 MW400 MW2027: 342 MW2027342 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027342 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Gresham House Cockenzie BESS240 MW0 MW31 Jul 20272gate 2Under Construction/Commissioning
2Cockenzie BESS102 MW240 MW31 Jul 20272gate 2Under Construction/Commissioning

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20272342 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Gresham House Cockenzie BESSBattery storage240 MW31 Jul 2027Under Construction/Commissioning
Cockenzie BESSBattery storage102 MW31 Jul 2027Under Construction/Commissioning

Supported by National Energy SO Open Data