MARES

Developer as published, connection site, reference: Maresconnect Limited. Bodelwyddan 400kV Substation (NGET). PRO-000978.

Sign in to watch this project
Capacity750 MWInterconnector
Connection date30 Nov 2028Status as printed: Awaiting Consents
First date seen 1 Apr 2025, difference +1339 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20282029File dated 2022-02-15: connection date 2028-11-30Nov 2028File dated 2026-10-20: connection date 2028-11-3015 Feb202220 Oct2026
20282029File dated 2022-02-15: connection date 2028-11-30Nov 2028File dated 2026-10-20: connection date 2028-11-3015 Feb202220 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 15 Feb 2022 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data