N84 Grid

Bodelwyddan 400kV Substation

NESO connection site, host NGET.

Contracted here4.22 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date30 Nov 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue4,218.4 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
MARES15 Feb 202230 Nov 2028750 MW
Mona Offshore Wind Farm31 May 202431 Oct 20291,500 MW
Moelfre Energy Park31 May 202431 Oct 2029158.4 MW
Bodelwyddan BESS and PV31 May 202431 Oct 2029110 MW
Awel Y Mor31 May 20241 Mar 20301,100 MW
St Asaph SSE31 May 20241 Nov 2037600 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.5 GW5.0 GW2028: 750 MW2029: 2.5 GW2030: 3.6 GW2037: 4.2 GW2028203020322034203620374.2 GW
0 MW2.5 GW5.0 GW2028: 750 MW2029: 2.5 GW2030: 3.6 GW2037: 4.2 GW20282031203420374.2 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028750 MW
20292,518.4 MW
20303,618.4 MW
20374,218.4 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1MARES750 MW0 MW30 Nov 2028not statedgate not printedAwaiting Consents
2Mona Offshore Wind Farm1,500 MW750 MW31 Oct 2029not statedgate not printedScoping
3Moelfre Energy Park158.4 MW2,250 MW31 Oct 20291gate 1Scoping
4Bodelwyddan BESS and PV110 MW2,408.4 MW31 Oct 2029not statedgate not printedScoping
5Awel Y Mor1,100 MW2,518.4 MW1 Mar 2030not statedgate not printedScoping
6St Asaph SSE600 MW3,618.4 MW1 Nov 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281750 MW
202931,768.4 MW
203011,100 MW
20371600 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Mona Offshore Wind FarmOffshore wind1,500 MW31 Oct 2029Scoping
Awel Y MorOffshore wind1,100 MW1 Mar 2030Scoping
MARESInterconnector750 MW30 Nov 2028Awaiting Consents
St Asaph SSEHybrid600 MW1 Nov 2037Scoping
Moelfre Energy ParkBattery storage158.4 MW31 Oct 2029Scoping
Bodelwyddan BESS and PVHybrid110 MW31 Oct 2029Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.