N84 Grid

Beauly 132/33 kV GSP Substation

NESO connection site, host SHET.

Contracted here0.13 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 May 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue126.9 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lovat Estate BESS27 Sep 202431 May 202649.9 MW
Tarvie Wind Farm22 Jul 202530 Oct 203377 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 50 MW2033: 127 MW20262027202820292030203120322033127 MW
0 MW100 MW200 MW2026: 50 MW2033: 127 MW2026202820302033127 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202649.9 MW
2033126.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lovat Estate BESS49.9 MW0 MW31 May 20262gate 2Consents Approved
2Tarvie Wind Farm77 MW49.9 MW30 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026149.9 MW
2033177 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Farr Wind Farm - TomatinOnshore wind92 MWnot statedBuilt
Tarvie Wind FarmHybrid77 MW30 Oct 2033Scoping
Lovat Estate BESSBattery storage49.9 MW31 May 2026Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.