The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Newtack Farm
7 Nov 2025 to 31 Oct 2033 (gate 1) - Riverside Bungalow Farm
7 Nov 2025 to 31 Oct 2033 (gate 1) - Keith BESS
7 Nov 2025 to 31 Oct 2033 (gate 1) - Backmuir Farm BESS
7 Nov 2025 to 31 Oct 2033 (gate not printed) - DAVIDSON FARM PV AND BESS
7 Nov 2025 to 31 Oct 2035 (gate 1) - Seggiecrook PV and BESS
7 Nov 2025 to 31 Oct 2035 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Newtack Farm | 7 Nov 2025 | 31 Oct 2033 | 49.9 MW |
| Riverside Bungalow Farm | 7 Nov 2025 | 31 Oct 2033 | 49.9 MW |
| Keith BESS | 7 Nov 2025 | 31 Oct 2033 | 50 MW |
| Backmuir Farm BESS | 7 Nov 2025 | 31 Oct 2033 | 49.5 MW |
| DAVIDSON FARM PV AND BESS | 7 Nov 2025 | 31 Oct 2035 | 45 MW |
| Seggiecrook PV and BESS | 7 Nov 2025 | 31 Oct 2035 | 66.32 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2033 | 199.3 MW |
| 2035 | 310.62 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Newtack Farm | 49.9 MW | 0 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
| 2 | Riverside Bungalow Farm | 49.9 MW | 49.9 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
| 3 | Keith BESS | 50 MW | 99.8 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
| 4 | Backmuir Farm BESS | 49.5 MW | 149.8 MW | 31 Oct 2033 | not stated | gate not printed | Scoping |
| 5 | DAVIDSON FARM PV AND BESS | 45 MW | 199.3 MW | 31 Oct 2035 | 1 | gate 1 | Scoping |
| 6 | Seggiecrook PV and BESS | 66.32 MW | 244.3 MW | 31 Oct 2035 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2033 | 4 | 199.3 MW |
| 2035 | 2 | 111.32 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Seggiecrook PV and BESS | Hybrid | 66.32 MW | 31 Oct 2035 | Scoping |
| Keith BESS | Battery storage | 50 MW | 31 Oct 2033 | Scoping |
| Riverside Bungalow Farm | Battery storage | 49.9 MW | 31 Oct 2033 | Scoping |
| Newtack Farm | Battery storage | 49.9 MW | 31 Oct 2033 | Scoping |
| Backmuir Farm BESS | Battery storage | 49.5 MW | 31 Oct 2033 | Scoping |
| DAVIDSON FARM PV AND BESS | Hybrid | 45 MW | 31 Oct 2035 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.