N84 Grid

Bolney 400kV Substation

NESO connection site, host NGET.

Contracted here1.80 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date29 May 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,804.4 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Bolney (tertiary)31 May 202429 May 202857 MW
Rampion Extension Offshore Wind Farm31 May 202431 Dec 20291,200 MW
Bolney31 May 202431 Jan 203147.5 MW
Hookers Farm BESS31 May 202431 Oct 2031250 MW
Bolney Farm31 May 202430 Oct 2037200 MW
Kingsfold21 Mar 202530 Oct 203749.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2028: 57 MW2029: 1.3 GW2031: 1.6 GW2037: 1.8 GW2028203020322034203620371.8 GW
0 MW1.0 GW2.0 GW2028: 57 MW2029: 1.3 GW2031: 1.6 GW2037: 1.8 GW20282031203420371.8 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202857 MW
20291,257 MW
20311,554.5 MW
20371,804.4 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Bolney (tertiary)57 MW0 MW29 May 20281gate 1Scoping
2Rampion Extension Offshore Wind Farm1,200 MW57 MW31 Dec 2029not statedgate not printedScoping
3Bolney47.5 MW1,257 MW31 Jan 2031not statedgate not printedScoping
4Hookers Farm BESS250 MW1,304.5 MW31 Oct 2031not statedgate not printedConsents Approved
5Bolney Farm200 MW1,554.5 MW30 Oct 20371gate 1Scoping
6Kingsfold49.9 MW1,754.5 MW30 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028157 MW
202911,200 MW
20312297.5 MW
20372249.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Rampion Extension Offshore Wind FarmOffshore wind1,200 MW31 Dec 2029Scoping
ShorehamGas460 MWnot statedBuilt
Hookers Farm BESSBattery storage250 MW31 Oct 2031Consents Approved
Bolney FarmHybrid200 MW30 Oct 2037Scoping
Bolney (tertiary)Hybrid57 MW29 May 2028Scoping
KingsfoldHybrid49.9 MW30 Oct 2037Scoping
Bolney (PIVOTED POWER LLP)Hybrid47.5 MW31 Jan 2031Scoping
CONTEGO Battery Storage ProjectBattery storage35.8 MWnot statedBuilt
Bolney Grid Stability ServicesReactive compensation0 MW31 Oct 2031Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.