N84 Grid

Bolney (PIVOTED POWER LLP)

Developer as published, connection site, reference: PIVOTED POWER LLP. Bolney 400kV Substation (NGET). PRO-001031.

Sign in to watch this project
Capacity47.5 MWHybrid
Connection date31 Jan 2031Status as printed: Scoping
First date seen 31 Oct 2027, difference +1188 dayscalculated by N84
MW ahead in N84's order at this site1,257 MWcalculated by N84

Connection date, edition by edition

20312032File dated 2024-05-31: connection date 2031-01-31Jan 2031File dated 2026-10-20: connection date 2031-01-3131 May202420 Oct2026
20312032File dated 2024-05-31: connection date 2031-01-31Jan 2031File dated 2026-10-20: connection date 2031-01-3131 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.