N84 Grid

Braintree 400kV Substation

NESO connection site, host NGET.

Contracted here1.66 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date30 Oct 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,656.9 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Braintree31 May 202430 May 202749.9 MW
Braintree31 May 202430 May 20277.1 MW
Braintree (Tertiary)31 May 202430 Oct 202649.9 MW
Bulls Lodge Farm 231 May 202430 Mar 2033350 MW
Bulls Lodge Farm31 May 202430 Apr 2033200 MW
Braintree31 May 202431 Oct 20341,000 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2026: 50 MW2027: 107 MW2033: 657 MW2034: 1.7 GW202620282030203220341.7 GW
0 MW1.0 GW2.0 GW2026: 50 MW2027: 107 MW2033: 657 MW2034: 1.7 GW20262029203220341.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202649.9 MW
2027106.9 MW
2033656.9 MW
20341,656.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Braintree49.9 MW0 MW30 May 20272gate 2Consents Approved
2Braintree7.1 MW49.9 MW30 May 20272gate 2Consents Approved
3Braintree (Tertiary)49.9 MW57 MW30 Oct 2026not statedgate not printedConsents Approved
4Bulls Lodge Farm 2350 MW106.9 MW30 Mar 20331gate 1Scoping
5Bulls Lodge Farm200 MW456.9 MW30 Apr 20331gate 1Scoping
6Braintree1,000 MW656.9 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026149.9 MW
2027257 MW
20332550 MW
203411,000 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Braintree (Braintree 10 Renewables Limited)Hybrid1,000 MW31 Oct 2034Scoping
Bulls Lodge Farm 2Hybrid350 MW30 Mar 2033Scoping
Bulls Lodge FarmHybrid200 MW30 Apr 2033Scoping
Braintree (PIVOTED POWER LLP)Hybrid57 MW30 May 2027Consents Approved
Indaver Rivenhall IWMFBiomass and waste55 MWnot statedBuilt
Braintree (Tertiary)Hybrid49.9 MW30 Oct 2026Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.