The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Braintree
31 May 2024 to 30 May 2027 (gate 2) - Braintree
31 May 2024 to 30 May 2027 (gate 2) - Braintree (Tertiary)
31 May 2024 to 30 Oct 2026 (gate not printed) - Bulls Lodge Farm 2
31 May 2024 to 30 Mar 2033 (gate 1) - Bulls Lodge Farm
31 May 2024 to 30 Apr 2033 (gate 1) - Braintree
31 May 2024 to 31 Oct 2034 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Braintree | 31 May 2024 | 30 May 2027 | 49.9 MW |
| Braintree | 31 May 2024 | 30 May 2027 | 7.1 MW |
| Braintree (Tertiary) | 31 May 2024 | 30 Oct 2026 | 49.9 MW |
| Bulls Lodge Farm 2 | 31 May 2024 | 30 Mar 2033 | 350 MW |
| Bulls Lodge Farm | 31 May 2024 | 30 Apr 2033 | 200 MW |
| Braintree | 31 May 2024 | 31 Oct 2034 | 1,000 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 49.9 MW |
| 2027 | 106.9 MW |
| 2033 | 656.9 MW |
| 2034 | 1,656.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Braintree | 49.9 MW | 0 MW | 30 May 2027 | 2 | gate 2 | Consents Approved |
| 2 | Braintree | 7.1 MW | 49.9 MW | 30 May 2027 | 2 | gate 2 | Consents Approved |
| 3 | Braintree (Tertiary) | 49.9 MW | 57 MW | 30 Oct 2026 | not stated | gate not printed | Consents Approved |
| 4 | Bulls Lodge Farm 2 | 350 MW | 106.9 MW | 30 Mar 2033 | 1 | gate 1 | Scoping |
| 5 | Bulls Lodge Farm | 200 MW | 456.9 MW | 30 Apr 2033 | 1 | gate 1 | Scoping |
| 6 | Braintree | 1,000 MW | 656.9 MW | 31 Oct 2034 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 49.9 MW |
| 2027 | 2 | 57 MW |
| 2033 | 2 | 550 MW |
| 2034 | 1 | 1,000 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Braintree (Braintree 10 Renewables Limited) | Hybrid | 1,000 MW | 31 Oct 2034 | Scoping |
| Bulls Lodge Farm 2 | Hybrid | 350 MW | 30 Mar 2033 | Scoping |
| Bulls Lodge Farm | Hybrid | 200 MW | 30 Apr 2033 | Scoping |
| Braintree (PIVOTED POWER LLP) | Hybrid | 57 MW | 30 May 2027 | Consents Approved |
| Indaver Rivenhall IWMF | Biomass and waste | 55 MW | not stated | Built |
| Braintree (Tertiary) | Hybrid | 49.9 MW | 30 Oct 2026 | Consents Approved |