Braintree (PIVOTED POWER LLP)

Developer as published, connection site, reference: PIVOTED POWER LLP. Braintree 400kV Substation (NGET). PRO-001042.

Sign in to watch this project
Capacity57 MWHybrid, Gate 2
Connection date30 May 2027Status as printed: Consents Approved
First date seen 30 Oct 2024, difference +942 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20242025202620272028File dated 2026-09-11: connection date 2024-10-30Oct 2024File dated 2026-10-20: connection date 2027-05-30May 202711 Sep202620 Oct2026
20242025202620272028File dated 2026-09-11: connection date 2024-10-30Oct 2024File dated 2026-10-20: connection date 2027-05-30May 202711 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Consents Approved (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 254Receipt: NESO TEC Register, file dated 11 Sep 2026, row 251
  2. 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO TEC Register, file dated 20 Oct 2026, row 254Receipt: NESO TEC Register, file dated 11 Sep 2026, row 251
  3. 20 Oct 2026. MW Effective From printed as 30 May 2027 (previous file: 30 Oct 2026), 212 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +212 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 254Receipt: NESO TEC Register, file dated 11 Sep 2026, row 251
  4. 20 Oct 2026. Project Status printed as Consents Approved (previous file: Awaiting Consents). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedAwaiting Consents → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 253Receipt: NESO TEC Register, file dated 11 Sep 2026, row 250
  5. 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO TEC Register, file dated 20 Oct 2026, row 253Receipt: NESO TEC Register, file dated 11 Sep 2026, row 250
  6. 20 Oct 2026. MW Effective From printed as 30 May 2027 (previous file: 30 Oct 2024), 942 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +942 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 253Receipt: NESO TEC Register, file dated 11 Sep 2026, row 250

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.