N84 Grid

Branxton 400kV Substation

NESO connection site, host SPT.

Contracted here4.68 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date31 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue4,510 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Branxton PV & BESS Station31 May 202431 Oct 20281,000 MW
Berwick Bank Offshore Wind Farm A31 May 202431 Oct 20281,150 MW
Branxton Energy Storage Facility31 May 202413 May 2029750 MW
Berwick Bank Offshore Wind Farm A31 May 202431 Oct 2029230 MW
Berwick Bank Offshore Wind Farm B31 May 202431 Oct 20291,150 MW
Berwick Bank Offshore Wind Farm B31 May 202430 Jun 2031230 MW
Springfield Solar and Battery31 May 202431 Oct 2031166.61 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.5 GW5.0 GW2028: 2.2 GW2029: 4.3 GW2031: 4.7 GW20282029203020314.7 GW
0 MW2.5 GW5.0 GW2028: 2.2 GW2029: 4.3 GW2031: 4.7 GW20282029203020314.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20282,150 MW
20294,280 MW
20314,676.61 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Branxton PV & BESS Station1,000 MW0 MW31 Oct 20281gate 1Scoping
2Berwick Bank Offshore Wind Farm A1,150 MW1,000 MW31 Oct 2028not statedgate not printedScoping
3Branxton Energy Storage Facility750 MW2,150 MW13 May 2029not statedgate not printedScoping
4Berwick Bank Offshore Wind Farm A230 MW2,900 MW31 Oct 2029not statedgate not printedScoping
5Berwick Bank Offshore Wind Farm B1,150 MW3,130 MW31 Oct 2029not statedgate not printedScoping
6Berwick Bank Offshore Wind Farm B230 MW4,280 MW30 Jun 2031not statedgate not printedScoping
7Springfield Solar and Battery166.61 MW4,510 MW31 Oct 2031not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202822,150 MW
202932,130 MW
20312396.61 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Berwick Bank Offshore Wind Farm AOffshore wind1,380 MW31 Oct 2029Scoping
Berwick Bank Offshore Wind Farm BOffshore wind1,380 MW30 Jun 2031Scoping
Branxton PV & BESS StationBattery storage1,000 MW31 Oct 2028Scoping
Branxton Energy Storage FacilityBattery storage750 MW13 May 2029Scoping
Springfield Solar and BatteryHybrid166.61 MW31 Oct 2031Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.