Breakish 132kV Substation

NESO connection site, host SHET.

Contracted here0.10 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 May 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue99.8 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Breakish Windfarm31 May 202431 May 202950 MW
Breakish Windfarm31 May 202430 Apr 203449.8 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2029: 50 MW2034: 100 MW202920302031203220332034100 MW
0 MW50 MW100 MW2029: 50 MW2034: 100 MW2029203120332034100 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202950 MW
203499.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Breakish Windfarm50 MW0 MW31 May 20291gate 1Scoping
2Breakish Windfarm49.8 MW50 MW30 Apr 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2029150 MW
2034149.8 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Breakish WindfarmOnshore wind99.8 MW30 Apr 2034Scoping

Supported by National Energy SO Open Data