N84 Grid

Cnoc Buidhe 132kV/33kV Substation

NESO connection site, host SHET.

Contracted here0.22 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date2 Apr 2030Date printed in the register

The queue, in order

Order calculated by N84
First in queue220 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Cnoc Buidhe Wind Farm31 May 20242 Apr 2030150 MW
Cnoc Buidhe Wind Farm31 May 202431 Oct 203470 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2030: 150 MW2034: 220 MW20302031203220332034220 MW
0 MW125 MW250 MW2030: 150 MW2034: 220 MW203020322034220 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2030150 MW
2034220 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Cnoc Buidhe Wind Farm150 MW0 MW2 Apr 2030not statedgate not printedScoping
2Cnoc Buidhe Wind Farm70 MW150 MW31 Oct 2034not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20301150 MW
2034170 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Cnoc Buidhe Wind FarmHybrid220 MW31 Oct 2034Scoping

Supported by National Energy SO Open Data