The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Port of Mostyn
31 May 2024 to 1 Dec 2030 (gate 1) - Port of Mostyn
31 May 2024 to 1 Jun 2031 (gate 1) - Port of Mostyn
31 May 2024 to 1 Jan 2032 (gate 1) - Icewind Connah's Quay
31 May 2024 to 1 Nov 2033 (gate 1) - Western MPI
5 Nov 2024 to 31 Oct 2037 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Port of Mostyn | 31 May 2024 | 1 Dec 2030 | 70 MW |
| Port of Mostyn | 31 May 2024 | 1 Jun 2031 | 70 MW |
| Port of Mostyn | 31 May 2024 | 1 Jan 2032 | 70 MW |
| Icewind Connah's Quay | 31 May 2024 | 1 Nov 2033 | 1,000 MW |
| Western MPI | 5 Nov 2024 | 31 Oct 2037 | 1,500 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2030 | 70 MW |
| 2031 | 140 MW |
| 2032 | 210 MW |
| 2033 | 1,210 MW |
| 2037 | 2,710 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Port of Mostyn | 70 MW | 0 MW | 1 Dec 2030 | 1 | gate 1 | Scoping |
| 2 | Port of Mostyn | 70 MW | 70 MW | 1 Jun 2031 | 1 | gate 1 | Scoping |
| 3 | Port of Mostyn | 70 MW | 140 MW | 1 Jan 2032 | 1 | gate 1 | Scoping |
| 4 | Icewind Connah's Quay | 1,000 MW | 210 MW | 1 Nov 2033 | 1 | gate 1 | Scoping |
| 5 | Western MPI | 1,500 MW | 1,210 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2030 | 1 | 70 MW |
| 2031 | 1 | 70 MW |
| 2032 | 1 | 70 MW |
| 2033 | 1 | 1,000 MW |
| 2037 | 1 | 1,500 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Western MPI | Interconnector | 1,500 MW | 31 Oct 2037 | Scoping |
| Connah's Quay (Uniper UK Limited) | Gas | 1,380 MW | not stated | Built |
| Icewind Connah's Quay | Offshore wind | 1,000 MW | 1 Nov 2033 | Scoping |
| Port of Mostyn | Tidal and wave | 210 MW | 1 Jan 2032 | Scoping |
| Deeside Power Station | Battery storage | 190 MW | 25 Oct 2026 | Built |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.