Developer as published, connection site, reference: National Grid Interconnector Holdings Limited. Connah's Quay 400kV Substation (NGET). PRO-003463.

Sign in to watch this project
Capacity1,500 MWInterconnector, Gate 1
Connection date31 Oct 2037Status as printed: Scoping
MW ahead in N84's order at this site1,210 MWcalculated by N84

Connection date, edition by edition

20372038File dated 2024-11-05: connection date 2037-10-31Oct 2037File dated 2026-10-20: connection date 2037-10-315 Nov202420 Oct2026
20372038File dated 2024-11-05: connection date 2037-10-31Oct 2037File dated 2026-10-20: connection date 2037-10-315 Nov202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 5 Nov 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 22 Jul 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO Interconnector Register, file dated 20 Oct 2026, row 36Receipt: NESO Interconnector Register, file dated 22 Jul 2025, row 34