Drakelow 400kV Substation

NESO connection site, host NGET.

Contracted here3.37 GWNot yet connected, as printed
Entries in the queue11entries with a printed MW
Earliest connection date1 Oct 2020Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue1,401.3 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Oaklands Farm Solar PV31 May 202430 Jun 2027162.3 MW
Royle Farm BESS22 Jul 202531 Oct 202890 MW
Powersite @ Drakelow31 May 20241 Oct 2020380 MW
Drakelow31 May 20241 Dec 2027120 MW
Drakelow Green Energy Centre31 May 202430 Apr 2028400 MW
Caldwell Road31 May 202430 Oct 2028249 MW
Drakelow Green Energy Centre31 May 202430 Oct 2029625 MW
Greta III31 May 202430 Oct 2029500 MW
Walton Road Energy Project31 May 202431 Oct 2029240 MW
Drakelow BESS31 May 202431 Dec 2029200 MW
Drakelow PV & BESS Station31 May 202430 Oct 2037400 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2020: 380 MW2027: 662 MW2028: 1.4 GW2029: 3.0 GW2037: 3.4 GW20202023202620292032203520373.4 GW
0 MW2.0 GW4.0 GW2020: 380 MW2027: 662 MW2028: 1.4 GW2029: 3.0 GW2037: 3.4 GW20202025203020373.4 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2020380 MW
2027662.3 MW
20281,401.3 MW
20292,966.3 MW
20373,366.3 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Oaklands Farm Solar PV162.3 MW0 MW30 Jun 20272gate 2Consents Approved
2Royle Farm BESS90 MW162.3 MW31 Oct 20282gate 2Consents Approved
3Powersite @ Drakelow380 MW252.3 MW1 Oct 2020not statedgate not printedUnder Construction/Commissioning
4Drakelow120 MW632.3 MW1 Dec 20271gate 1Scoping
5Drakelow Green Energy Centre400 MW752.3 MW30 Apr 2028not statedgate not printedAwaiting Consents
6Caldwell Road249 MW1,152.3 MW30 Oct 20281gate 1Scoping
7Drakelow Green Energy Centre625 MW1,401.3 MW30 Oct 2029not statedgate not printedAwaiting Consents
8Greta III500 MW2,026.3 MW30 Oct 2029not statedgate not printedConsents Approved
9Walton Road Energy Project240 MW2,526.3 MW31 Oct 20291gate 1Scoping
10Drakelow BESS200 MW2,766.3 MW31 Dec 2029not statedgate not printedConsents Approved
11Drakelow PV & BESS Station400 MW2,966.3 MW30 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20201380 MW
20272282.3 MW
20283739 MW
202941,565 MW
20371400 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Drakelow Green Energy CentreHybrid1,025 MW30 Oct 2029Awaiting Consents
Greta IIIHybrid500 MW30 Oct 2029Consents Approved
Drakelow PV & BESS StationHybrid400 MW30 Oct 2037Scoping
Powersite @ DrakelowGas380 MW1 Oct 2020Under Construction/Commissioning
Caldwell RoadBattery storage249 MW30 Oct 2028Scoping
Walton Road Energy ProjectHybrid240 MW31 Oct 2029Scoping
Drakelow BESSBattery storage200 MW31 Dec 2029Consents Approved
Oaklands Farm Solar PVHybrid162.3 MW30 Jun 2027Consents Approved
Drakelow (ENSO GREEN HOLDINGS V LIMITED)Battery storage120 MW1 Dec 2027Scoping
Royle Farm BESSBattery storage90 MW31 Oct 2028Consents Approved