Easterhouse 275/33kV Substation

NESO connection site, host SPT.

Contracted here0.21 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Jun 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue209.79 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Whitehill Battery Storage31 May 202430 Oct 2028200 MW
Easterhouse GSP7 Nov 202530 Jun 20270.99 MW
Easterhouse GSP7 Nov 202530 Apr 20298.8 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2027: 1 MW2028: 201 MW2029: 210 MW202720282029210 MW
0 MW125 MW250 MW2027: 1 MW2028: 201 MW2029: 210 MW202720282029210 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20270.99 MW
2028200.99 MW
2029209.79 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Whitehill Battery Storage200 MW0 MW30 Oct 20282gate 2Consents Approved
2Easterhouse GSP0.99 MW200 MW30 Jun 2027not statedgate not printedScoping
3Easterhouse GSP8.8 MW200.99 MW30 Apr 2029not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202710.99 MW
20281200 MW
202918.8 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Whitehill Battery StorageBattery storage200 MW30 Oct 2028Consents Approved
Easterhouse GSP (SP DISTRIBUTION PLC)Hybrid9.79 MW30 Apr 2029Scoping