Capacity9.79 MWHybrid
Connection date30 Apr 2029Status as printed: Scoping
First date seen 30 Jun 2027, difference +670 dayscalculated by N84
First date seen 30 Jun 2027, difference +670 dayscalculated by N84
MW ahead in N84's order at this site200 MWcalculated by N84
Connection date, edition by edition
No date history to draw
The files N84 holds in your history window print no connection date for this project.
Observed changes
N84 holds 2 editions of the NESO Embedded Register back to 7 Nov 2025. No change for this record is older than 30 days.
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. MW Effective From printed as 30 Apr 2029 (previous file: blank). N84 holds no copy between 7 Nov 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedReceipt: NESO Embedded Register, file dated 20 Oct 2026, row 204Receipt: NESO Embedded Register, file dated 7 Nov 2025, row 204
- 20 Oct 2026. MW Effective From printed as 30 Jun 2027 (previous file: blank). N84 holds no copy between 7 Nov 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedReceipt: NESO Embedded Register, file dated 20 Oct 2026, row 203Receipt: NESO Embedded Register, file dated 7 Nov 2025, row 203