N84 Grid

Exeter 400kV Substation

NESO connection site, host NGET.

Contracted here2.48 GWNot yet connected, as printed
Entries in the queue8entries with a printed MW
Earliest connection date1 May 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue2,081.9 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Exeter BESS31 May 202430 Aug 2027290 MW
Exeter Main Tertiary31 May 20241 May 202457 MW
Tale Lane Solar / A008 Langford27 Sep 202415 Apr 202535 MW
Exeter (Tertiary)31 May 202416 Jun 202849.9 MW
FAB Link Interconnector15 Feb 202230 Sep 20321,250 MW
Exeter Main31 May 202428 Oct 2033400 MW
Exeter (Tertiary)31 May 20246 Dec 20367.1 MW
Exeter BESS31 May 202431 Oct 2037390 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2024: 57 MW2025: 92 MW2027: 382 MW2028: 432 MW2032: 1.7 GW2033: 2.1 GW2036: 2.1 GW2037: 2.5 GW20242026202820302032203420372.5 GW
0 MW1.3 GW2.5 GW2024: 57 MW2025: 92 MW2027: 382 MW2028: 432 MW2032: 1.7 GW2033: 2.1 GW2036: 2.1 GW2037: 2.5 GW20242028203220372.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202457 MW
202592 MW
2027382 MW
2028431.9 MW
20321,681.9 MW
20332,081.9 MW
20362,089 MW
20372,479 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Exeter BESS290 MW0 MW30 Aug 20272gate 2Consents Approved
2Exeter Main Tertiary57 MW290 MW1 May 2024not statedgate not printedScoping
3Tale Lane Solar / A008 Langford35 MW347 MW15 Apr 2025not statedgate not printedScoping
4Exeter (Tertiary)49.9 MW382 MW16 Jun 2028not statedgate not printedAwaiting Consents
5FAB Link Interconnector1,250 MW431.9 MW30 Sep 2032not statedgate not printedAwaiting Consents
6Exeter Main400 MW1,681.9 MW28 Oct 20331gate 1Scoping
7Exeter (Tertiary)7.1 MW2,081.9 MW6 Dec 2036not statedgate not printedScoping
8Exeter BESS390 MW2,089 MW31 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024157 MW
2025135 MW
20271290 MW
2028149.9 MW
203211,250 MW
20331400 MW
203617.1 MW
20371390 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
FAB Link InterconnectorInterconnector1,250 MW30 Sep 2032Awaiting Consents
Exeter Solar PV & BESSBattery storage680 MW31 Oct 2037Scoping
Exeter MainHybrid400 MW28 Oct 2033Scoping
Exeter (Tertiary)Hybrid57 MW6 Dec 2036Scoping
Exeter Main TertiaryThermal57 MW1 May 2024Scoping
Tale Lane Solar / A008 LangfordHybrid35 MW15 Apr 2025Scoping
Water LaneGas20.88 MWnot statedBuilt
Peak Gen Makro ExeterReactive compensation20 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.